As a matter of policy, EPS takes pre-construction, in-progress and completion photos for all projects we have been awarded. In an effort to provide you with a better understanding of the types of construction projects EPS provides, we have provided project photos in each of our individual trade categories i.e. Environmental Service, General Engineering and General Building.
In July 2007 EPS was awarded a contract with the BNSF Railway to provide site remediation services for a parcel of land known as the RANA Station Project. The RANA Station Project was located along the BNSF right-of-way in Colton, California. The project consisted of the removal of approximately 15,000 cubic yards of lead contaminated soil. This involved excavating to depths varying from 2'-8' ft. throughout the site. The excavated soil was stockpiled, loaded and transported to an approved disposal facility in Arizona. EPS imported clean soil for backfilling and regrading of the project site. Project duration was approximately (3) months from start to finish.